White Constructions v PBS Holdings Revisited

White Constructions Pty Ltd v PBS Holdings Pty Ltd [2019] NSWSC 1166, involved a claim for delay and costs arising out of a contract to design a sewerage system for a subdivision and submit it for approval. The alleged breach was the failure to create and submit a sewer design acceptable to the approval authority which had the effect of delaying completion of the subdivision, giving rise to a claim for damages by White.

White and PBS both appointed experts to undertake a schedule analysis, and they did agree an ‘as-built’ program of the works but disagreed on almost everything else including the delay analysis method to use, the correct application of the methods, and the extent of the overall project delay caused by the delays in approving the sewer design.

The Judge found:

[Clause 18]      Plainly, both experts are adept at their art. But both cannot be right. It is not inevitable that one of them is right.
[Note: This approach is consistent with the UK court decision of Akenhead J in Walter Lilly & Company Ltd v Mckay [2012] EWHC 1773 (TCC) at [377], “the court is not compelled to choose only between the rival approaches and analyses of the experts. Ultimately it must be for the court to decide as a matter of fact what delayed the works and for how long”. This precedent has been followed on a number of occasions[1].]

[Clause 22]      The expert reports are complex. To the unschooled, they are impenetrable. It was apparent to me that I would need significant assistance to be put in a position to critically evaluate their opinions and conclusions.

[Clause 25]      Under UCPR r 31.54, the Court obtained the assistance of Mr Ian McIntyre (on whose appointment the parties agreed).

[Clause 137]   The major components of the works were:
       • earthworks,
       • roadworks and kerbing,
       • sewerage,
       • electrical and National Broadband Network (NBN) installation,
       • footpaths, and
       • landscaping.,

[Clause 138]   The electrical and NBN installation was contracted to and carried out by an organisation called Transelect. Landscaping was contracted to RK Evans Landscaping Pty Ltd. The as-built program is not in dispute.
[Note: the rest of the work was undertaken by other contractors]

[Clause 184]   White bears the onus of establishing that it suffered loss and the quantum of it.

[Clause 185]   White’s damages are based on delay to the whole project, said to be attributable to the late (underbore) sewer design. This is not the type of subject upon which precise evidence cannot be adduced. [Therefore] It is not a subject which involves the Court having to make an estimation or engage in some degree of guesswork.

[Clause 188]   The descriptions of the methods adopted by Shahady and Senogles respectively are evidently derived from the publication of the United Kingdom Society of Construction Law, the Delay and Disruption Protocol….

[Clause 191]   Mr McIntyre’s opinion, upon which I propose to act, is that for the purpose of any particular case, the fact that a method appears in the Protocol does not give it any standing, and the fact that a method, which is otherwise logical or rational, but does not appear in the Protocol, does not deny it standing.
[Note: this is the same wording as an express statement contained in the Delay and Disruption Protocol]

[Clause 195]   Mr McIntyre’s opinion, upon which I propose to act, is that neither method [used by the parties experts] is appropriate to be adopted in this case.

[Clause 196]   Mr McIntyre’s opinion, upon which I propose to act, is that close consideration and examination of the actual evidence of what was happening on the ground will reveal if the delay in approving the sewerage design actually played a role in delaying the project and, if so, how and by how much. In effect, he advised that the Court should apply the common law common sense approach to causation In effect, he advised that the Court should apply the common law common sense approach to causation referred to by the High Court in March v E & MH Stramare Pty Ltd (1991) 171 CLR 506.

[Clause 197]   The Court is concerned with common law notions of causation. The only appropriate method is to determine the matter by paying close attention to the facts, and assessing whether White has proved, on the probabilities, that delay in the underboring solution delayed the project as a whole and, if so, by how much.

[Clause 198]   This requires it to establish that:
• the whole project would have been completed by 15 July 2016,
• the final sewer approval delay delayed sewer works,
• the sewer works delay prevented non-sewer works from otherwise proceeding, that is, that the programme could not reasonably have been varied to accommodate the consequences of late approval, and
• other works could not have been done to fill downtimes so as to save time later.

[Clause 199]   ……… White has failed to discharge this burden.

Summary

The factors required to prove a delay outlined by the Judge at Clause 198 can be generalised as follows:

  1. The completion date for the project before the delay event occurred has to be known with some certainty.
  2. The delay event has to be shown to cause a delay which flowed through to extend the overall project completion date.
  3. There were not reasonable alternative ways of working that could mitigate the effect of the delay on project completion.

More significant, none of these steps needs a CPM schedule.  The project status and the effect of the disruption on project completion can be assessed based on its effect on the productivity of key resources. This is discussed in Assessing Delays in Agile & Distributed Projects: https://mosaicprojects.com.au/PDF_Papers/P215_Assessing_Delays_In_Agile_+_Distributed_Projects.pdf   


[1]     This approach by the courts is discussed in Delivering Expert Evidence is Becoming Harder: https://mosaicprojects.com.au/Mag_Articles/AA028_Delivering_Expert_Evidence.pdf

The Artificial Intelligence Ecosystem

We have posted a number of times discussing aspects of Artificial Intelligence (AI) in project management, but what exactly is AI?  This post looks at the components in the AI ecosystem and briefly outlines what the various terms mean.

𝗔𝗿𝘁𝗶𝗳𝗶𝗰𝗶𝗮𝗹 𝗜𝗻𝘁𝗲𝗹𝗹𝗶𝗴𝗲𝗻𝗰𝗲: a range of computer algorithms and functions that enable computers and machines to mimic the problem-solving and decision-making capabilities of the human mind.

Automatic Programming: is a technology that enables computers to generate code or write programs with minimal human intervention.

Knowledge Representation: is concerned with representing information about the real world in a way that a computer can understand, so it can utilize this knowledge and behave intelligently.

Expert System: is a computer system emulating the decision-making ability of a human expert. A system typically includes: a knowledge base, an inference engine that applies logical rules to the knowledge base to deduce new information, an explanation facility, a knowledge acquisition facility, and a user interface.

Planning and Scheduling: an automated process that achieves the realization of strategies or action sequences that are complex and must be discovered and optimized in multidimensional space, typically for execution by intelligent agents, autonomous robots, and unmanned vehicles.

Speech Recognition: the ability of devices to respond to spoken commands. Speech recognition enables hands-free control of various devices, provides input to automatic translation, and creates print-ready dictation.

Intelligent Robotics: robots that function as an intelligent machine and it can be programmed to take actions or make choices based on input from sensors.

Visual Perception: enables machines to derive information from, and understand images and visual data in a way similar to humans

Natural Language Processing (NLP): gives computers the ability to understand text and spoken words in much the same way human beings can.

Problem Solving & Search Strategies: Involves the use of algorithms to find solutions to complex problems by exploring possible paths and evaluating the outcomes. A search algorithm takes a problem as input and returns a solution in the form of an action sequence.

𝗠𝗮𝗰𝗵𝗶𝗻𝗲 𝗟𝗲𝗮𝗿𝗻𝗶𝗻𝗴: is concerned with the development and study of statistical algorithms that allow a machine to be trained so it can learn from the training data and then generalize to unseen data, to perform tasks without explicit instructions. There are three basic machine learning paradigms, supervised learning, unsupervised learning, and reinforcement learning.

• Supervised learning: is when algorithms learn to make decisions based on past known outcomes. The data set containing past known outcomes and other related variables used in the learning process is known as training data.

• Unsupervised learning: is a type of machine learning that learns from data without human supervision. Unlike supervised learning, unsupervised machine learning models are given unlabelled data and allowed to discover patterns and insights without any explicit guidance or instruction.

Reinforcement Learning (RL): is an interdisciplinary area of machine learning concerned with how an intelligent agent ought to take actions in a dynamic environment to maximize the cumulative reward.

Classification: a process where AI systems are trained to categorize data into predefined classes or labels.

K-Means Clustering: cluster analysis is an analytical technique used in data mining and machine learning to group similar objects into related clusters.

Principal Component Analysis (PCA): is a dimensionality reduction method used to reduce the dimensionality of large data sets, by transforming a large set of variables into a smaller one that still contains most of the information in the large set.

Automatic Reasoning: attempts to provide assurance about what a system or program will do or will never do based on mathematical proof.

Decision Trees:  is a flow chart created by a computer algorithm to make decisions or numeric predictions based on information in a digital data set.

Random Forest: is an algorithm that combines the output of multiple decision trees to reach a single result. It handles both classification and regression problems.

Ensemble Methods: are techniques that aim at improving the accuracy of results in models by combining multiple models instead of using a single model. The combined models increase the accuracy of the results significantly.

Naive Bayes: is a statistical classification technique based on Bayes Theorem. It is one of the simplest supervised learning algorithms.

Anomaly Detection: the identification of rare events, items, or observations which are suspicious because they differ significantly from standard behaviours or patterns.

𝗡𝗲𝘂𝗿𝗮𝗹 𝗡𝗲𝘁𝘄𝗼𝗿𝗸𝘀: are machine learning (ML) models designed to mimic the function and structure of the human brain and help computers gather insights and meaning from text, data, and documents by being trained to recognising patterns and sequences.

Large Language Model (LLM): is a type of neural network called a transformer program that can recognize and generate text, answer questions, and generate high-quality, contextually appropriate responses in natural language. LLMs are trained on huge sets of data.

Radial Basis Function Networks: are a type of neural network used for function approximation problems. They are distinguished from other neural networks due to their universal approximation and faster learning speed.

Recurrent Neural Networks (RNN): is a type of neural network where the output from the previous step is used as input to the current step. In traditional neural networks, all the inputs and outputs are independent of each other. For example, when it is required to predict the next word of a sentence, the previous words are required and hence there is a need to remember the previous words.

Autoencoders: is a type of neural network used to learn efficient coding of unlabelled data (unsupervised learning). An autoencoder learns two functions: an encoding function that transforms the input data into code, and a decoding function that recreates the input data from the encoded representation.

Hopfield Networks: is a recurrent neural network having synaptic connection pattern such that there is an underlying Lyapunov function (method of stability) for the activity dynamics. Started in any initial state, the state of the system evolves to a final state that is a (local) minimum of the Lyapunov function.

Modular Neural Networks: are characterized by a series of independent neural networks moderated by some intermediary to allow for more complex management processes.

Adaptive Resonance Theory (ART): is a theory developed to address the stability-plasticity dilemma. The terms adaptive and resonance means that it can adapt to new learning (adaptive) without losing previous information (resonance).

Deep Learning:  is a method in artificial intelligence (AI) that teaches computers to process data in a way that is inspired by the human brain. Deep learning models can recognize complex patterns in pictures, text, sounds, and other data to produce accurate insights and predictions. The adjective deep refers to the use of multiple layers in the network.

Transformer Model:  is a neural network that learns context and thus meaning by tracking relationships in sequential data by applying an evolving set of mathematical techniques to detect subtle ways even distant data elements in a series influence and depend on each other.

Convolutional Neural Networks (CNN): is a regularized type of feed-forward neural network that learns feature engineering by itself via filters or kernel optimization.

Long Short-Term Memory Networks (LSTM): is a recurrent neural network (RNN), aimed to deal with the vanishing gradient problem present in traditional RNNs.

Deep Reinforcement Learning: is a subfield of machine learning that combines reinforcement learning (RL) and deep learning.

Generative Adversarial Networks (GAN): is a class of machine learning frameworks for approaching generative AI. Two neural networks contest with each other in the form of a zero-sum game, where one agent’s gain is another agent’s loss.  Given a training set, this technique learns to generate new data with the same statistics as the training set. A GAN trained on photographs can generate new photographs that look at least superficially authentic.

Deep Belief Networks (DBN): are a type of neural network that is composed of several layers of shallow neural networks (RBMs) that can be trained using unsupervised learning. The output of the RBMs is then used as input to the next layer of the network, until the final layer is reached. The final layer of the DBN is typically a classifier that is trained using supervised learning. DBNs are effective in applications, such as image recognition, speech recognition, and natural language processing.

For more discussion on the use of AI in project management see:
https://mosaicprojects.com.au/PMKI-SCH-033.php#AI-Discussion

One Defence Data – Another ‘Big Consultant’ issue?

Hidden in the pre-Christmas holiday fun, the ABC[1] published an ‘investigations exclusive’ by Linton Besser and defence correspondent Andrew Greene[2] that needs more attention.

It appears project ICT2284 (One Defence Data), a $515 million project to unify and exploit the data resources held by the Department of Defence is in trouble due to Hastie (pun intended) decisions made before the last election. Within this overall project, a $100 million One Defence Data “systems integrator” contract was awarded to KPMG Australia Technologies Solutions on the eve of the last federal election, and the then assistant minister for defence, Andrew Hastie, announced KPMG’s contract, promising it would “deliver secure and resilient information systems”.

This award was made after KPMG had been paid $93 million Between 2016 and 2022, for consulting work on a range of strategic advice, which included the development of ICT2284 and its failed forerunner, known as Enterprise Information Management, or EIM.

Unsurprisingly, the review by Anchoram Consulting highlighted both governance and procedural issues including:

  • The project has been plagued by a “lack of accountability” and conflicts of interest.
  • The documents suggest there is profound confusion inside Defence about who is in charge and what is actually being delivered.
  • Core governance documents have not been signed off and key requirements of KPMG’s contract have been diluted from “mandatory” to “desirable”, sometimes in consultation with KPMG itself.
  • The project had been “retrospectively” designed to justify a $100 million contract that was issued to KPMG Australia Technologies Solutions, or KTech, exposing the department to “significant risk”.

The heart of ICT2284’s problem appears to be the project’s fundamental design work had “not been done due to … the rush to meet deadlines tied to the Cabinet submission and related procurement activities”, with “no understood and agreed, desired end-state”.

Predictably both the area of Defence running the project, known as CIOG, or the Chief Information Officer Group, and KPMG reject the report findings.

The full ABC report is at: https://amp.abc.net.au/article/103247476

From a governance perspective the biggest on-going issue appears to be the lack of capability within CIOG and government generally to manage this type of complex project. The downsizing and deskilling of the public service has been on-going for decades (under both parties). This means the outsourcing of policy development to the big consultancies is inevitable, and their advice will be unavoidably biased towards benefitting them.

The actions by the current government to reverse this trend are admirable but will take years to be effective. In the meantime, we watch.

For more on governance failures see: https://mosaicprojects.com.au/PMKI-ORG-005.php#Process4

For good governance practice see: https://mosaicprojects.com.au/PMKI-ORG-005.php#Process3


[1] Australian Broadcasting Corporation

[2] Posted Tue 19 Dec 2023 at 6:41pm:

A Brief History of Agile

The history of agile software development is not what most people think, and is nothing like the story pushed by most Agile Evangelists.

Our latest publication A Brief History of Agile shows that from the beginning of large system software development the people managing the software engineering understood the need for prototyping and iterative and incremental development. This approach has always been part of the way good software is developed.

The environment the authors of the early papers referenced and linked in the article were operating in, satellite software and ‘cold-war’ control systems, plus the limitations of the computers they were working on, did require a focus on testing and documentation – it’s too late for a bug-fix once WW3 has started…..  But this is no different to modern day control systems development where people’s lives are at stake. Otherwise, nothing much has changed, good software is built incrementally, and tested progressively,  

The side-track into ‘waterfall’ seems to have bee started by people with a focus on requirements management and configuration management, both approached from a document heavy bureaucratic perspective. Add the desire of middle-management for the illusion of control and you get waterfall imposed on software developers by people who knew little about the development of large software systems. As predicted in 1970, ‘doing waterfall’ doubles to cost of software development. The fact waterfall survives in some organisations through to the present time is a factor of culture and the desire for control, even if it is an illusion.

The message from history, echoed in the Agile Manifesto, is you need to tailor the documentation, discipline, and control processes, to meet the requirements of the project. Developing a simple website with easy access to fix issues is very different to developing the control systems for a satellite that is intended to work for years, millions of miles from earth.

To read the full article and access many of the referenced papers and third-party analysis see: https://mosaicprojects.com.au/PMKI-ZSY-010.php#Agile