Monday

Tag Archives: claims

Costain vs Haswell Revisited

One of the ways the law tries to maintain consistency across multiple court cases in literally hundreds of court rooms is by following the same decision-making process used in previous cases to decide an outcome where similar matters are in dispute. This has the advantage of providing a degree of certainty, or at least consistency in the way laws and contracts are interpreted. But can make the law relatively slow to change when business practice changes. However, there are times when the Judges identify problems well before the practitioners! Costain Ltd v Charles Haswell & Partners Ltd [2009] EWHC B25 (TCC) (24 September 2009) is one example. This case related to the construction of the eleven separate structures, that constitute the Lostock and Rivington Water Treatment Works in Lancashire, UK.

As part of this court case, the design and construction contractor, Costain Limited, sought costs from its consulting civil engineer, Charles Haswell & Partners Ltd (Haswell), for the cost of delays caused by incorrect geotechnical advice provided by Haswell. Costain alleged that Haswell’s original design for pre-foundation ground treatment works failed to achieve the specified design criteria for two of the eleven project structures. This resulted in the need for unplanned piling works to support the two structures, which Costain alleged caused a critical delay to the project. As a consequence, Costain was seeking to recover the costs of the delay (prolongation costs) from Haswell.

The quantum experts in the case agreed on two tests for establishing Costain’s entitlement to prolongation costs:

  • First, whether the assumed delay to completion caused by the remedial piling had crystallised into the same actual delay to the completion of the project some sixteen months later, and
  • Second, whether all of the project’s activities were delayed by the piling to just two of the eleven structures.

The parties’ programming experts agreed on a common methodology for assessing the delay, which the judgment refers to as a ‘time impact analysis’ or ‘windows slice analysis’. The method described in the judgement appears the same as the Time Impact Analysis defined in the SCL Delay and Disruption Protocol and AACEi MIP 3.7 (for more detail on this see: https://mosaicprojects.com.au/PDF_Papers/P216_Assessing_Delay_The_SCL_Options.pdf).

There were some points of disagreement between the experts but ultimately, the Court found that the remedial piling on two structures was critical to the project at the time considered in the ‘windows analysis’  noting the experts have agreed that the delays to the RGF and IW were critical delays since those buildings were on the critical path of the project at the relevant time.  Ordinarily therefore one would expect, other things being equal, that the project completion date would be pushed out at the end of the job by the same or a similar period to the period of delay to those buildings.  However, as experience shows on construction sites, many supervening events can take place which will falsify such an assumed result.  For example, the Contractor may rearrange his programme so that other activities are accelerated or carried out in a different sequence thereby reducing the initial delays. [Clause 233]

The assumption underpinning the expert’s ‘window’ analysis showing that a critical delay had occurred and the entitlement to a delay was based on the premise that the work on the rest of the project would follow the logic as shown in the CPM network. The Court rejected this assumption because the assumed flow-on of the delay to the overall completion of the works was not demonstrated: ‘I find that it has not been shown by Costain that the critical delay caused to the project by the late provision of piled foundations to the RGF and IW buildings necessarily pushed out the contract completion date by that period or at all’. [Clause 200 (ii)]

The second test asked whether a delay to work on part of the project would cause all of the project’s activities to be prolonged. In considering this test, the Court rejected Costain’s assumption that the remedial piling to two of the structures on the project prolonged all eleven structures: ‘If the contractor establishes [a critical, excusable delay], he is entitled to an extension of time to the whole project including, of course all those activities which were not in fact delayed … But the contractor will not recover the general site overheads of carrying out all the activities on site as a matter of course unless he can establish that the delaying event to one activity in fact impacted on all the other site activities’. [Clause 183-184]

The Court also found no evidence has been called to establish that the delaying events in question in fact caused delay to any activities on site apart from the RGF and IW buildings.  That being so, it follows, in my judgment, that the prolongation claim advanced by Costain based on recovery of the whole of the site costs of the Lostock site, fails for want of proof’. [Clause 185]

Costain failed in its claim for time related prolongation costs and only recovered the additional costs of installing the piled foundations, because ‘In the absence of any analysis between all the operative delays from the start to the finish, which is absent in this case, in my judgment it is simply not possible for the Court to be satisfied on the balance of probabilities that the assumption upon which this part of Costain’s case depends, is correct’. [Clause 235]

Conclusion – Distributed Projects are Different!

The fundamental problem outlined above was caused by the distributed nature of the project work. The Critical Path Method (CPM) assumes there is one best way to accomplish the work of the project and this is described in the schedule. In distributed projects there are multiple different ways the work could be accomplished. Therefore, any delay analysis technique based on the assumption that the sequence of work shown in a CPM schedule is the only way to accomplish the work is unlikely to prove the delay.  A different approach is needed!

We are working on this challenge.

  • Scheduling Challenges in Agile & Distributed Projects defines the problem and classifies four different types of project from a CPM and controls perspective. Using this classification, the Lostock and Rivington Water Treatment Works was a ‘Class 4’ project where a CPM schedule was imposed, but is unlikely to prove effective. Distributed projects fall under Class3, where a detailed CPM schedule is not accepted as an effective controls approach – different processes are needed.

  • Predicting Completion in Agile & Distributed Projects (due for publication in the May edition of PMWJ) will define a process for measuring progress and predicting completion in Class 3 projects.

  • Assessing Delays in Agile & Distributed Projects (due for publication in the June edition of PMWJ) will define a process for reliably determining the effect of delay or disruption in Class 3 projects.  

As work progresses, we will be updating the Schedule control in Agile and Distributed projects section of the Mosaic website and welcome feedback: https://mosaicprojects.com.au/PMKI-SCH-010.php#Issues-A+D  

The full Costain judgement can be downloaded from: https://mosaicprojects.com.au/PMKI-ITC-020.php#Cases

Assessing Delay and Disruption Updated

One of our core papers focused on dispute management has been updated as part of a refresh for this part of the Mosaic web resources. Assessing Delay and Disruption – Tribunals Be-Ware was designed to help ADR and legal professionals understand the options available to disputants in assessing ‘delay’ to help them quickly cut through the fog of expertise present in many major disputes to achieve a speedy determination. It has also proved useful for both project and senior managers confronted with the need to defend or make a claim.

This paper is based on the AACE® International Recommended Practice No. 29R-03, Forensic Schedule Analysis (RP29-03), published 25th April 2011. Unfortunately, there seems to be an increasing divergence between this approach to delay claims which seems to be preferred in the USA and jurisdictions that follow US precedent, and the approach embedded in the Society of Construction Law Delay and Disruption Protocol, 2nd edition, which the UK courts and many Commonwealth jurisdictions, including Australia, are increasingly tending to prefer.

This update is a work in progress. To download this paper and others click through to: https://mosaicprojects.com.au/PMKI-ITC-020.php#ADD

All papers are available for use free of charge under a Creative Commons licence.

Delivering Expert Evidence is Becoming Harder

Delivering effective Expert Evidence is becoming harder, at least in the UK, Australia and most likely other Commonwealth jurisdictions.  Traditionally the role of a Judge was to apply the law to the evidence presented by the parties to a dispute. In the case of expert evidence, this could include expert opinion, and where experts disagree, the Judge could choose one expert’s views over another, or combine the views. This approach seems to be changing with significant implications for the experts when preparing their reports and evidence.

It now seems acceptable in the UK and Australia that ‘the court is not compelled to choose only between the rival approaches and analyses of the experts. Ultimately it must be for the court to decide [what occurred] as a matter of fact… from a common-sense perspective’.

Our latest article: Delivering Expert Evidence is Becoming Harder discusses a number of recent judgements that seem to have re-framed the challenge of delivering effective expert evidence in the UK, Australia and potentially many other jurisdictions. Download the article from: https://mosaicprojects.com.au/PMKI-ITC-020.php#Process2

Concurrent Delays – UK High Court Decision Supports SCL Protocol

Our White Paper Concurrent and Parallel Delays sets out the basic framework for considering this complex area of contract law. Download from: https://mosaicprojects.com.au/WhitePapers/WP1064_Concurrent-Delays.pdf

A recent decision by the English and Wales High Court in Thomas Barnes & Sons PLC v Blackburn with Darwen Borough Council [2022] EWHC 2598 (TCC), confirms the contentions in our White Paper, and brings a breath of common sense to the consideration of EOTs and the associated delay costs when there are delays occurring in parallel.

The central elements of the dispute arose out of a contract between Blackburn with Darwen Borough Council (Council) and Thomas Barnes & Sons Plc (TB) to construct a new bus terminal in Blackburn (Project). The Project suffered significant cost increases and delays for which TB claimed extensions of time. The Council denied TB’s claims, terminated the construction contract for delay and appointed a replacement contractor to complete the works. TB subsequently commenced proceedings against the Council for monies said to be due under the contract on a proper valuation of the works done at termination (including delay costs due to prolongation) as well as damages for wrongful termination.

The case revolved around two competing causes of delay to the Project. The first, which supported TB’s EOT claim and for which the Council was responsible, was caused by deflection issues within the steelwork that required investigation and remediation which ultimately delayed subsequent activities on the critical path. The second, for which TB was responsible, arose out of delays to TB’s roof covering works, which the Council alleged caused concurrent delay to the critical path at the same time as the steel deflection delay.

Both parties relied on expert delay evidence and each expert adopted methodologies in the Society of Construction Law Delay and Disruption Protocol to undertake their respective analyses. The judge, in assessing the methods of the opposing experts, stated that ‘[109]. ….irrespective of which method of delay analysis is deployed, there is an overriding objective of ensuring that the conclusions derived from that analysis are sound from a common-sense perspective‘. As a consequence of the experts’ diverging opinions, the judge stated that the court would need to come to its own conclusion as to whether the steel deflection delay and the roof covering delay were concurrent.

Despite the fact that the roof covering delay was resolved while the steel deflection delay was ongoing (and did not cause an independent delay to the critical path), the court determined that the delays were in fact concurrent, stating:

‘[140]. In my judgment this is a case where these causes were concurrent over the period of delay caused by the roof coverings. That is because completion of the remedial works to the hub structural steelwork was essential to allow the concrete topping to be poured and the hub SFS to be installed, without which the hub finishes could not be meaningfully started, but completion of the roof coverings was also essential for the hub finishes to be meaningfully started as well. It is not enough for the claimant to say that the works to the roof coverings were irrelevant from a delay perspective because the specification and execution of the remedial works to the hub structural steelwork were continuing both before and after that period of delay. Conversely, it is not enough for the defendant to say that the remedial works to the hub structural steelwork were irrelevant from a delay perspective because the roof coverings were on the critical path. The plain fact is that both of the work items were on the critical path as regards the hub finishes and both were causing delay over the same period.’  Further, the court stated that TB could not seek to use the steel deflection delay as ‘a convenient hook on which to seek to hang all of the delay to the works’. To do so ignored the fact that there was also a problem caused by the delays TB suffered to the roof coverings, which was itself a cause of delay to the critical path.

When considering concurrency, the Society of Construction Law Delay and Disruption Protocol, 2nd edition (SLC Protocol) simply requires the delays and their effects (or parts of the delays and their effects) to be experienced at the same time for concurrency to exist. It has two relevant sections which appear to have been followed by the Judge:

10. Concurrent delay – effect on entitlement to EOT

True concurrent delay is the occurrence of two or more delay events at the same time, one an Employer Risk Event, the other a Contractor Risk Event, and the effects of which are felt at the same time. For concurrent delay to exist, each of the Employer Risk Event and the Contractor Risk Event must be an effective cause of Delay to Completion (i.e. the delays must both affect the critical path). Where Contractor Delay to Completion occurs or has an effect concurrently with Employer Delay to Completion, the Contractor’s concurrent delay should not reduce any EOT due.

14. Concurrent delay – effect on entitlement to compensation for prolongation

Where Employer Delay to Completion and Contractor Delay to Completion are concurrent and, as a result of that delay the Contractor incurs additional costs, then the Contractor should only recover compensation if it is able to separate the additional costs caused by the Employer Delay from those caused by the Contractor Delay. If it would have incurred the additional costs in any event as a result of Contractor Delay, the Contractor will not be entitled to recover those additional costs.

Applying the fundamental principal in the SLC Protocol that separates disruption and delay costs from the consideration of EOTs, the court held that:
(n) EOT and prolongation – conclusion [157]. The claimant is entitled to an additional EOT of 119 days (or 17 weeks), but to prolongation of only 27 days. After allowing for the EOTs already granted and agreed, which take the completion date to 13 April 2015, that would entitle the claimant to a revised completion date of 10 August 2015.

The overall period of the roof covering delay included a 31 day delay in starting the roof covering work and an increased duration of the roof works of 26 days compared to the original plan. In considering these contractor delays, the judgement seems to imply ‘pacing’ is not a valid basis for not considering (or reducing) concurrent contractor delays that are in parallel with client delays. TBs expert claimed: “there may have been some works to the externals that could be progressed, however this would not change my opinion that the [steel] works were critical in delay and that it was within TBS’s gift to pace any non-critical works”.

The Judge in considering this opinion stated: ‘[133]. If by this [the expert] meant to suggest that the roof coverings could have been progressed but they were non-critical and could have been performed in a more leisurely manner as a result, this seems to me to ignore the fundamental fact that throughout the crucial period from October 2014 through to January 2015 the claimant could not have known how long the remedial works to the hub steelworks would take and could not therefore reasonably have proceeded on the basis that there was no need to worry about the roof coverings until the hub steel deflection issue was completely resolved’. This part of the judgement clearly sets a high bar for any ‘pacing’ claim to be successful.

Also, implicit in the court’s reasoning is a rejection of the ‘first in time’ approach to assessing concurrent delay in favour of the pragmatic approach in the SCL Protocol that does not allow either party to benefit from a fault on its part. 

These decisions are likely to be significant in the UK, Australia and most Commonwealth Jurisdictions. For more on concurrent and parallel delays see: https://mosaicprojects.com.au/PMKI-ITC-020.php#Concurrent.

An augmented version of this post is now available at: https://mosaicprojects.com.au/Mag_Articles/AA027_Concurrent_Delays-UK_High_Court.pdf

Another aspect of this and several other judgements dealing with the way expert evidence is being treated by the courts can be downloaded from: https://mosaicprojects.com.au/Mag_Articles/AA028_Delivering_Expert_Evidence.pdf

Assessing Delay and Disruption

In preparation for the IAMA National conference later this week I have just finished developing and updating a short series of papers focused on addressing schedule delay and disruption.

  • Assessing Delay and Disruption – an overview of the accepted methods of forensic schedule analysis [ view the paper ]
  • Prolongation, Disruption and Acceleration Costs – an overview of the options for calculating costs associated with approved delays and acceleration [ view the paper ]
  • The complexities around concurrent and parallel delays are discussed on Mosaic’s White Paper WP1064 Concurrent and Parallel Delays

Any comments are welcome.

Using a Risk Management approach for Assessing Claims

One of the more difficult management decisions is how hard to pursue a contract claim. The claim will inevitably have a deleterious impact on a key stakeholder relationship and any significant claim will have proportionally high costs associated with legal and other expenses. Balancing the inevitable costs against the possible gains is a difficult but necessary decision before moving forward. Usually, the potential yield of a claim is given as a subjective assessment based on experience.

Dr. John Lancaster of Hill International has recently published a paper that seeks to remove the subjectivity from the assessment of which claims are worth pursuing (see 1 below). Lancaster proposes using a risk assessment approach to determine the likely range of outcomes and which claims contribute the most to the likely settlement. He suggests using the following factors:

  • Entitlement confidence:
    • The strength of the contractual argument for entitlement; and
    • Contractually compliant notices.
  • Magnitude confidence:
    • The quality and quantity of supporting records;
    • The quality of the project schedules (and any necessary corrections and/or repairs), cost records, etc; and
    • The certainty with which the effect/s of each event is known.

Applying a percentage weighting to these factors and using Monte Carlo analysis the likely range of cost and time outcomes can be assessed and the key claims identified.

It is important that the right people complete this assessment: the entitlement confidence categories should be assessed by counsel and the magnitude confidence categories assessed by the domain experts with input from the project staff.

The results of this analysis will identify:

  • The likely outcomes under the prevailing entitlement and magnitude confidence ratings;
  • The probabilities of securing different outcomes; and
  • Identifying the claims that are the most important to the overall claim and which ones require more work.

Based on this assessment and after factoring in the costs and consequences of making the claim, pragmatic decisions can be made on:

  • whether or not to pursue a claim;
  • where to set negotiation limits (see 2 below); and
  • which of the claims, with more work on establishing entitlement and/or substantiation, could contribute the most to a robust claim.

In an ideal world effective stakeholder relationship management would remove the need for contractual claims. When they become necessary, Dr. Lancaster’s ideas will help remove much of the unnecessary ‘heat’ from the assessment process and provide a pragmatic baseline for managing any claim in a professional and business like way.

  1. Lancaster, John, “The use of risk analysis techniques to evaluate potential delay claim outcomes,” Project Control Professional: The Journal of the Association of Cost Engineers, February 2010. The full article is available on request from johnlancaster@hillintl.com.
  2. For more on dispute management and negotiating see: http://www.mosaicprojects.com.au/WhitePapers/WP1049_Dispute_Management.pdf