Monday

Tag Archives: Scheduling

Critical Path Scheduling – 4 Things People Don’t Get

Over the last few weeks, I’ve seen more rubbish published about CPM from supposed experts than usual.  The false assertions range from statement claiming CPM does not include resource analysis to ones confusing basic resource scheduling processes.

So here are a few supported facts:

  1. The Critical Path Method (CPM), and PERT (Program Evaluation and Review Technique) both started out as ‘activity-on-arrow’ networks in 1957. The Precedence Diagramming Method (PDM) uses an activity-on-node’ notation, and was published in 1962 as a manual technique but was quickly applied to both PERT and CPM networks by the computer companies developing CPM and PERT software (by 1965 everything had merged into ‘all encompassing’ software packages). See: https://mosaicprojects.com.au/PMKI-ZSY-030.php
  2. The two fundamental differences between CPM and PERT are:
    1. CPM uses a single deterministic duration estimate, PERT uses three duration estimates and is used to assess the probability of achieving a milestone.
    2. CPM was built to resolve resourcing issues on plant shutdowns for Du Pont, PERT/Time did not include resources until the introduction of PERT/Cost in 1961. PERT/Cost used a single resource estimate. See: https://mosaicprojects.com.au/PMKI-ZSY-020.php#EVM
  3. Resource analysis uses time analysis calculations as a basis for its resource calculations:
    1. Aggregation: sums the resource requirements per day based on time analysis dates (usually early start)
    2. Smoothing: levels resource demand by using the available float. Some resource overloads will be reduced or eliminated by using float to shift non-critical activities back in time. The project end date and other constraints do not change, which means in some situations resource overloading may still occur.
    3. Leveling: delays critical tasks and the project completion to avoid overloading. See:
      https://mosaicprojects.com.au/PMKI-SCH-013.php#Process5

The ‘lean construction’ salesmen promoting the lie CPM does not include resources are simply wrong. What is true are a lot of schedulers develop schedules without resources, resource balancing in a CPM schedule is difficult, and there are now better options for resource optimization available in some tools. But many contracts and the USA GAO require resource loaded schedules.  Similarly, there are a number of ‘experts’ confusing resource smoothing and levelling (there seems to be quite a few). To correct their error, all they need to do is simply read a standard – the PMBOK® Guide (6th Ed.) is a good starting point and is consistent with all other credible authorities for the last 50+ years.

  • The purpose of a CPM schedule is also confused by many experts. Every schedule is a simple model of how work on a project may unfold in the future. This means the schedule cannot be completely accurate:
    • The schedule is a simplified representation, it contains a few hundred, or thousand activities that summarize the millions of actions that the project team will actually do to complete the work.
    • Every duration and resource estimate is an assessment of what may happen in the future. The unknown is the degree of error in each estimate, and overall.
    • The project team may, or may not, follow the planned sequence of work.

So, what’s the point of developing a schedule?  As Prof. George Box pointed out in “Time Series Analysis – Forecasting and Control” (page 285): “All models are approximations, and no model form can ever represent the truth absolutely. Given sufficient data, statistical tests can discredit models that could nevertheless be entirely adequate for the purpose at hand. Alternatively, tests can fail to indicate serious departures from assumptions because of small sample sizes or because these tests are insensitive to the types of discrepancies that occur. The best policy is to devise the most sensitive statistical procedures possible but be prepared to employ models that exhibit slight lack of fit. If diagnostic checks, which have been thoughtfully devised, are applied to a model fitted to a reasonably large body of data and fail to show serious discrepancies, then we should feel comfortable using that model.”  This and a number of similar quotes by him are often paraphrased as ‘All models are wrong, but some are useful’. A well-constructed CPM schedule can be extremely useful if it is used to:

  • Obtain agreement from the project team and resource suppliers on how the work will be done,
  • For assessing risk and identifying issues early,
  • Measuring performance against the plan and identifying variances,
  • Testing options to overcome negative variances and then obtaining buy-in to implement the recovery action.

But the CPM schedule will only be useful, if it is used by the project team to communicate, agree, and coordinate their work. The bigger the project, the more important this communication, agreement, and buy-in becomes. This is a dynamic, adaptive, agile, process. Focusing on what was thought to be a good idea last year embedded in a fossilized ‘contact program’ that does not change may keep claims consultants in a job, but it won’t help finish the project on time. If the schedule is not working on your project, it is a management and skills issue, changing to a different tool will not solve either of these factors.

One of my objectives in publishing Easy CPM was to make a low cost, easy-to-read resource available to schedulers who want to lift their skills – fixing management is a more interesting challenge. For more on Easy CPM see: https://mosaicprojects.com.au/shop-easy-cpm.php.

Finally, to answer the last question, borrowing from Group Captain Sir Douglas Bader: “Schedules are for the guidance of wise people and the obedience of fools!”  They provide insight, not control, and can be extremely useful if they are used!

The Planning Paradox – How much detail is too much?

Traditional views tend to favor a management approach built on the assumption that more detail is better – and to a point, this is undoubtedly correct. Insufficient detail in a plan of any type is a sure way to fail; ‘just do it’ at the overall project level does not help. But, finessing project plans to present useful information at the right level of detail is not easy – decisions have to be made!

Balancing the factors shown in this diagram helps make the right decision. As the risk environment increases, the project controls need to be more rigorous. The risk environment is influenced by the size or significance of the identified risks, and the overall degree of uncertainty associated with the work. As either (or both) of these factors increase, the controls systems need to be more rigorous.

The two factors that influence the degree of rigour in the controls system are the amount of detail included (granularity) and the frequency of the monitoring, reviewing and updating of the plans. But, as suggested above, too much detail will increase costs and reduce efficiency and effectiveness.

There’s no right answer to this paradox, our latest article The Planning Paradox – How much detail is too much? offers some useful guidelines to consider (download the article).

For more on Schedule Strategy, Planning, & Design, see: https://mosaicprojects.com.au/PMKI-SCH-011.php  

CPM Anomalies Invalidate Monte Carlo

A couple of weeks ago I posted on some of the anomalies in CPM logic that will cause unexpected results: CPM Scheduling – the logical way to error #1. A comment on the post by Santosh Bhat started me thinking about the effect of these logical constructs on risk analysis.

The various arrangement of activities and links shown in CPM Scheduling – the logical way to error #1 (with the addition of a few more non-controlling links) follow all of the scheduling rules tested by DCMA and other assessments. The problem is when you change the duration of a critical activity, there is either no effect or the reverse effect on the overall schedule duration.

In this example, the change in the overall project duration is the exact opposite of the change in the duration of Activity B (read the previous post for a more detailed explanation).  For this discussion, it is sufficient to know that an increase of 2 weeks in the duration of ‘B’ results in a reduction of the overall project duration of 2 weeks (and vice-versa).

The effect these anomalies on the voracity of a Monte Carlo analysis is significant. The essence of Monte Carlo is to analyze a schedule 100s of times using different activity durations selected from a pre-determined range that represents the uncertainty associated with each of the identified risks in a schedule. If the risk event occurs, or is more serious, the affected activity duration in increased appropriately (see more on Monte Carlo). 

In addition to calculating the probability of completing by any particular date, most Monte Carlo tools also generate tornado charts showing the comparative significance of each risk included in the analysis and its effect on the overall calculation.  For example, listing the risks that have the strongest correlation between the event occurring and the project being delayed.  

Tornado charts help the project’s management to focus on mitigating the most significant risks.

When a risk is associated with an activity that causes on of the anomalies outlined in CPM Scheduling – the logical way to error #1 the consequence is a reduction in the accuracy of the overall probability assessments, and more importantly to reduce the significance of the risk in tornado charts. The outcome of the anomalous modelling is to challenge the fundamental basis of Monte Carlo. There are more examples of similar logical inconsistencies, that will devalue Monte Carlo analysis, included in Section 3.5 of Easy CPM.

Easy CPM is designed for schedulers that know how to operate the tools efficiently, and are looking to lift their skills to the next level. The book is available for preview, purchase (price $35), and immediate download, from: https://mosaicprojects.com.au/shop-easy-cpm.php

CPM Scheduling – the logical way to error #1

Section 3.5 of Easy CPM looks at some of the logical scheduling errors that are easy to introduce into a schedule, and that for the most part will not show up in the automated checking tools applying test such as the DCMA 14 point assessment (see more on the DCMA assessment at: https://mosaicprojects.com.au/WhitePapers/WP1088_DCMA-14-Point.pdf)

The naming convention used below is borrowed from Miklos Hajdu.  In all cases the links shown in the diagram are the controlling links, in a ‘live’ schedule there are likely to be many other links as well.

Reverse Critical

In this logical configuration, the change in the overall project duration is the opposite of any change in the activity duration.

A reduction of 1-day in the duration of activity B will lengthen the project duration by one day, an increase of 1-day will reduce the project duration by one day.

Neutral Critical Open ends (dangles) have the effect of isolating the activity duration from the schedule. The project duration is unaffected by either a 1-day decrease, or a 1-day increase in the duration of activity B. There are two variants, SS and FF:

In both cases it does not matter what change is made to activity B, there is no change in the overall duration of the project.  This is one of the primary reasons almost every scheduling standard requires a link from a predecessor into the start of every activity and a link from the end of the activity to a successor, however, even with other links in place, if the control is through either of the scenarios above, the result is still the same.

Bi-critical Activities

Finally, for this post, any change in the duration of activity B will cause the project duration to increase.

A 1-day reduction of the duration of activity B will lengthen the project duration by one day, and an increase of 1-day will also lengthen the project duration by one day.  Bi-critical activities depend on having a balanced ladder where all of the links and activities are critical in the baseline schedule. Increasing the duration of B pushes the completion of C through the FF link. Reducing the duration of B pulls the SS link back to a later time and therefore delays the start of C.  The same effect will occur if the ladder is unbalanced or there is some float across the whole ladder, it is just not as obvious and may not flow through to a delay depending on the float values and the extent of the change.

Easy CPM

There are more examples of similar logical inconsistencies included in Section 3.5 of Easy CPM. Easy CPM is designed for schedulers that know how to operate the tools efficiently, and are looking to lift their skills to the next level. The book is available for preview, purchase (price $35), and immediate download, from: https://mosaicprojects.com.au/shop-easy-cpm.php  

Easy CPM launched

Easy CPM is a self-paced course-in-a-book, supported by Mosaic Project Services Pty Ltd, focused on developing and using an effective schedule in almost any software tool. For projects using EVM, Easy CPM acts as a companion to our Easy EVM focusing on developing the realistic and achievable schedule that underpins EVM and is needed for the successful delivery of all projects.

The book is intended to provide practical guidance to people involved in developing, or using, schedules based on the Critical Path Method (CPM). It is designed to act as a reference and practice guide to enhance the effectiveness of their scheduling practice after they have learned to use the CPM scheduling software of their choice.

The basic premise underpinning the development of this book is that a schedule is only useful if it is used. Creating a usable schedule requires two parallel processes:

  1. It requires a pragmatic approach to planning and scheduling the future work of a project to create a realistic and achievable schedule.
  2. It also requires management to make effective use of the schedule, which is a management challenge that typically involves a significant shift in culture and expectations.

Both of these aspects are considered in Easy CPM.

The book is divided into six sections, each section includes guidance on an aspect of CPM scheduling, references, and a set of 20 questions; with the answers in Section 7. Section 8 incorporates the appendix.

$35.00 AUD (Plus GST, Australian customers only). Size: 295 pages, 120 questions, file size 22 Mb.

Preview Easy CPM on Book2Look, or click through for more information and to buy.

See more on Easy EVM.

Scheduling Core Papers Updated

We’ve been working on a series of books:
Easy EVM is published: See more on the book
Easy CPM is a work in progress, publication later this year
Easy SHM will follow in 2022.

As part of the development of Easy CPM as course-in-a-book which is designed to act as a reference and practice guide for people implementing CPM scheduling after they have learned to use the CPM scheduling software of their choice. We have updated Mosaic’s ‘core scheduling papers‘; these are:
A Guide to Scheduling Good Practice
Attributes of a Scheduler
Dynamic Scheduling
Links, Lags & Ladders
Schedule Float
Schedule Levels
Schedule Calculations

These updated papers are available to download and use free of charge under a Creative Commons 3.0 license: Download the papers from https://mosaicprojects.com.au/PMKI-SCH-010.php

New Articles posted to the Web #90

We have been busy beavers updating the PM Knowledge Index on our website with Papers and Articles.   Some of the more interesting uploaded during the last couple of weeks include:

You are welcome to download and use this information under our free Creative Commons licence.

Visit our PMKI Library for free access to many more papers and articles: https://mosaicprojects.com.au/PMKI.php

New Articles posted to the Web #89

We have been busy beavers updating the PM Knowledge Index on our website with Papers and Articles.   Some of the more interesting uploaded during the last couple of weeks include:

You are welcome to download and use this information under our free Creative Commons licence.

Visit our PMKI Library for free access to many more papers and articles: https://mosaicprojects.com.au/PMKI.php

New Articles posted to the Web #88

We have been busy beavers updating the PM Knowledge Index on our website with Papers and Articles.   Some of the more interesting uploaded during the last couple of weeks include:

You are welcome to download and use this information under our free Creative Commons licence.

Visit our PMKI Library for free access to many more papers and articles: https://mosaicprojects.com.au/PMKI.php

Philosophies & Principles Used to Shape Planning Approaches

Any output from a planning process is a consequence of the approach applied by the planner to develop their plan.  Different people will develop different plans to achieve the same objectives based on their knowledge, experience and attitudes. This influence can be ignored or, if better understood, exploited!

This article outlines the fundamental principles and philosophies that can be used by planners to develop their plan: https://mosaicprojects.com.au/Mag_Articles/AA001_philosophies_of_planning.pdf

For more papers on schedule strategy and design see: https://mosaicprojects.com.au/PMKI-SCH-010.php#Process3